+91 9600 121 800

Plans

Dashboard

Daily & Speed

Quant

Verbal

DILR

Compete

Free Stuff

calendarBack
Quant

/

Arithmetic II

/

Time & Work

Time And Work

MODULES

Basics & Worker-Day Method
Worker-Day Method
Unitary Method
Relative Efficiencies
Negative Work, Alternating Work & Past Questions

CONCEPTS & CHEATSHEET

Concept Revision Video

SPEED CONCEPTS

Time & Work 1
-/10
Time & Work 2
-/10
Time & Work 3
-/10

PRACTICE

Time & Work : Level 1
Time & Work : Level 2
Time & Work : Level 3
ALL MODULES

CAT 2025 Lesson : Time & Work - Basics & Worker-Day Method

bookmarked

1. Introduction

In the entrance tests, about
111 to 222 questions are asked from this topic. This chapter is similar to Time, Speed and Distance. To draw parallels, the amount of work to be completed is similar to Distance, while the efficiency or rate of completion is similar to Speed. Time is a common element across both.

Typical variables that we come across in this chapter are as follows.

1) Work: Work can be defined as anything – making a toy, building a wall, completing an office project, filling a tank with water, etc.

2) Efficiency or rate of completion: This is the amount of work completed by a person in a unit of time. This is used in section 3. Unitary Method.

3) Number of people: Questions tend to include number of people or number of pipes doing a certain work. In certain questions the efficiencies or rates of completion are different.

Questions from this lesson can be solved using one of the following approaches.

1) Worker-Days Method: This method is used when there are many people in a group and they work at the same rate (or efficiency). Depending on the group and time period provided in the question, we will have to form units such as man-days, woman-days, man-hours, woman-hours, child-hours, etc.

2) Unitary Method: This method can be used for solving all other types of questions. In this method, we assign the total work to be done as
111. This helps us ascertain the efficiency at ease. For instance, if John takes 444 days to complete a piece of work, then his efficiency or rate of completion is 14th\dfrac{1}{4}^{\text{th}}41​th of the work in 111 day. Other extended concepts such as percentage completion and parts completion are extension of this method.

2. Worker-Day Method

This method applies for group(s) of workers, where each worker works at the same constant rate or efficiency. In this approach, work is defined as the number of days
111 worker takes to complete the work.

For instance, if 20 workers can complete a work in 5 days, then it means that it takes
20×5=20 \times 5 =20×5= 100 worker-days to complete the work. In other words, the work can be completed by 1 worker in 100 days or 100 workers in 1 day.

The questions of this type can be asked with different worker-types (like men, women, children, workers, typists, etc.) and different time periods (like months, weeks, hours, minutes, etc.)

Note: Unless stated otherwise, the efficiency or rate of completion of each worker is assumed to be the same.

We could also use variation and product constancy in solving these type of questions. Note that these two approaches will save time only when
222 sets of variables are involved (for instance, workers and time taken).

Example 1

If 666 men can complete a piece of work in 121212 days, how long does it take 888 men to complete the work?

Solution

Standard Worker-Days Approach

Work to be completed requires 6×12=6 \times 12 =6×12= 72 man-days.

Let
xxx be the number of days it takes 888 men to complete the work.

∴8×x=72\therefore 8 \times x = 72∴8×x=72

⇒
x=9 x = 9x=9

Alternatively (Variation)

Number of workers and time taken are inversely proportional (Refer Proportion & Variation lesson). As the work is constant, increase in workers reduces the time required to complete the work and vice-versa.



68=x12 \dfrac{6}{8} = \dfrac{x}{12} 86​=12x​ ⇒ x=9 x = 9x=9

Alternatively (Product Constancy)

Work completed (as man-days) is a constant and is the product of number of men and the number of days they work for. (For product constancy method refer Percentages lesson)

Increase in men by
13 \dfrac{1}{3}31​, will result in a decrease in days of 13+1=14 \dfrac{1}{3+1} = \dfrac{1}{4}3+11​=41​.

Days taken by
888 men =12−14×12=9= 12 - \dfrac{1}{4} \times 12 = 9=12−41​×12=9 days

Answer:
999 days


Where more than two variables are involved, like in the following example, the variation and product constancy methods might be time consuming. Please use the standard worker-day method in these cases.

Example 2

666 workers, working 888 hours a day, take 888 days to assemble a car. How many days would 999 workers working 444 hours a day take to assemble 333 cars?

Solution

We shall use worker-hours as the unit for work.

Assembling a car =6= 6=6 workers ×8\times 8×8 days ×8 hoursday=6×8×8\times 8 \space \dfrac{\text{hours}}{\text{day}} = 6 \times 8 \times 8×8 dayhours​=6×8×8 worker-hours

Assembling
333 cars =3×6×8×8= 3 \times 6 \times 8 \times 8=3×6×8×8 worker-hours

It is given that
999 workers work 444 hours/day to assemble 333 cars. Let ddd be the number of days taken by them.

∴9×x×4=3×6×8×8\therefore 9 \times x \times 4 = 3 \times 6 \times 8 \times 8∴9×x×4=3×6×8×8

⇒
x=3×6×8×89×4=32 x = \dfrac{3 \times 6 \times 8 \times 8}{9 \times 4} = 32x=9×43×6×8×8​=32

Answer:
323232

Note: Multiplying
3×6×8×8=11523 \times 6 \times 8 \times 8 = 11523×6×8×8=1152, and then dividing by 9×4=36 9 \times 4 = 369×4=36 would have taken more time.

Want to read the full content

Unlock this content & enjoy all the features of the platform

Subscribe Now arrow-right
videovideo-lock