calendarBack
Quant

/

Arithmetic II

/

Time & Work
ALL MODULES

CAT 2025 Lesson : Time & Work - Negative Work, Alternating Work & Past Questions

bookmarked

5. Negative rate of completion

Negative rate of completion questions are typically pipes, drains/leaks and tanks based. For instance, Pipe A and Pipe B can fill a tank in
22 hours and 44 hours while drain C can empty a tank in 66 hours. If all three are open at the same time, how long does it take to fill an empty tank?

In such questions the efficiency of a leak, or something undoing the work, will be negative.

Example 19

Tap X can fill a tank in 44 hours and tap Y can fill the same tank in 66 hours. A drain in the bottom of the tank can empty a full tank in 1212 hours. If the two taps and the drain are opened at the same time, how long does it take an empty tank to be filled?

Solution

Portion of tank filled by taps X and Y in 11 hour are 14\dfrac{1}{4} and 16\dfrac{1}{6} respectively.

Portion of tank emptied by the drain in
11 hour is 112\dfrac{1}{12}.

Portion of tank filled in
11 hour =14+16112=13= \dfrac{1}{4} + \dfrac{1}{6} - \dfrac{1}{12} = \dfrac{1}{3}

Time taken to fill the tank
=3= 3 hours

Alternatively

Let the tank's capacity be LCM
(4,6,12)=12(4, 6, 12) = 12 units.

Taps X and Y fill the tank at the rate of
124\dfrac{12}{4}= 3 units/hr and 126\dfrac{12}{6} = 2 units/hr respectively.

The drain empties the tank at the rate of
1212\dfrac{12}{12} = 1 unit/hr

When all are open, rate of filling
=3+21= 3 + 2 - 1 = 4 units/hr

Time taken to fill the tank
=124=3= \dfrac{12}{4} = 3 hours

Answer:
33 hours


Example 20

Pipes A and B take 55 hours and 88 hours respectively to fill an empty tank. Both the pipes are turned on at the same time. Exactly after two hours, a leak develops due to the pressure in the tank. It, therefore, takes 22 more hours for the tank to be filled. If the water flowing out of the leak was at a steady rate, how long would it take a filled tank to be emptied by the leak?

Solution

Let the leak take xx hours to empty the tank.

Portion of the tank filled by the
22 pipes in 22 hours is 2(15+18)=13202\left( \dfrac{1}{5} + \dfrac{1}{8} \right) = \dfrac{13}{20}

As it takes
22 more hours to fill the remainder of the tank, which is 12640=7201 - \dfrac{26}{40} = \dfrac{7}{20}.

2(15+181x)=7202 \left( \dfrac{1}{5} + \dfrac{1}{8} - \dfrac{1}{x} \right) = \dfrac{7}{20}

1340740=1x \dfrac{13}{40} - \dfrac{7}{40} = \dfrac{1}{x}

x=203 x = \dfrac{20}{3} = 6 hrs 40 mins

Alternatively

Let the tank's capacity be LCM
(5,8)=40(5, 8) = 40 units.

Pipes A and B fill the tank at the rate of
405\dfrac{40}{5} = 8 units/hr and 408\dfrac{40}{8} = 5 units/hr respectively.

Volume filled by A and B in
22 hours =2×(8+5)=26= 2 \times (8 + 5) = 26 units

Let the leak empty the tank at the rate of
x\bm{x} units/hr.
Volume of tank that is empty
=4026= 40 - 26 = 14 units

Volume filled by A, B and the leak in the next
22 hours =2×(8+5x)=14= 2 \times (8 + 5 - x) = 14

262x=14 26 - 2\text{x} = 14
x x = 6 units/hr

Time taken by the leak to empty the tank
=406=203= \dfrac{40}{6} = \dfrac{20}{3} = 6 hrs 40 mins

Answer:
66 hrs 4040 mins


Example 21

A pipe usually takes 33 hours to fill an empty tank with water. However, on a particular day, it took 7.57.5 hours to fill the tank due to a leak it had developed. Then, how many hours would the leak take to empty a full tank?

Solution

Let the time taken by the leak to empty a full tank be tt.

131t=17.5\dfrac{1}{3} - \dfrac{1}{t} = \dfrac{1}{7.5}1t=13215\dfrac{1}{t} = \dfrac{1}{3} - \dfrac{2}{15}

t=15 t = 15

Answer:
55

6. People or objects working alternately

These questions involve objects or group of objects with different efficiencies taking turns and working. In these questions you need to calculate the portion of work completed in a cycle and then find out the point where a single person or object's work would render the work complete. The Parts Method is best to use here.

Example 22

When working alone, A, B and C take 12,1512, 15 and 2424 days to complete a project. A works alone on the project on the first day, B works alone on the second day and C works alone on the third day. This pattern continues with each of the individuals working alone every 33 days. In how many days is the work completed?

Solution

Portion of work completed every 33 days =112+115+124=10+8+5120=23120= \dfrac{1}{12} + \dfrac{1}{15} + \dfrac{1}{24} = \dfrac{10 + 8 + 5}{120} = \dfrac{23}{120}

Let's look at the work as involving
120120 parts. A, B and C can finish 10,810, 8 and 55 parts in a day respectively and in 33 days 2323 parts of work get completed.

In 5 such cycles involving
1515 days, 5×23=1155 \times 23 = 115 parts get completed and 55 are remaining.

It's A's turn now, who can complete
1010 parts in a day. Since there are 55 parts left, A can complete in 510=0.5\dfrac{5}{10} = 0.5 day. Therefore, the work gets completed in 15.515.5 days.

Answer:
15.515.5


Example 23

A and C are pipes that take 1010 minutes and 6060 minutes to fill a tank. B and D are leaks that take 4040 and 2424 minutes to empty a tank. At any given time only a tap or a drain is open. A is turned on for the first minute, B is then turned on for the second minute, C for the third, D for the fourth, A for fifth, B for the sixth and so on. This is repeated till the tank is full. How long does it take for the tank to be filled?

Solution

In one cycle of 44 minutes, portion of tank filled =110140+160124=123+25120=6120= \dfrac{1}{10} - \dfrac{1}{40} + \dfrac{1}{60} - \dfrac{1}{24} = \dfrac{12 - 3 + 2 - 5}{120} = \dfrac{6}{120}

Once again, the denominator can be looked at as the total work (i.e., 120 parts). In one cycle of
44 minutes, 66 parts are filled. Parts of tank filled by Pipe A, Leak B, Pipe C and Leak D are +12,3,+2+12, -3, +2 and 5-5 respectively.

The maximum that a pipe can fill in
11 minute is Pipe A which is 1212 parts. So, we can find out the number of cycles that fill 12012=108120 - 12 = 108 parts to provide for the possibility of a pipe filling the rest of the tank.

Therefore, in
1818 cycles or 7272 minutes, 18×6=10818 \times 6 = 108 parts are filled and 1212 parts are remaining. As it is A's turn for the 73rd73^\text{rd} minute and it fills 1212 parts, the work is complete in 7373 minutes.

Answer:
7373 minutes

7. Past Questions

Question 1

There's a lot of work in preparing a birthday dinner. Even after the turkey is in oven, there are still the potatoes and gravy, yams, salad, and cranberries, not to mention setting the table. Three friends, Asit, Arnold, and Afzal, work together to get all of these chores done. The time it takes them to do the work together is six hours less than Asit would have taken working alone, one hour less than Arnold would have taken, and half the time Afzal would have taken working alone. How long did it take them to do these chores working together?
[CAT 2001]

2020 minutes
3030 minutes
4040 minutes
5050 minutes

Question 2

A water tank has M inlet pipes and N outlet pipes. An inlet pipe can fill the tank in 88 hours while an outlet pipe can empty the full tank in 1212 hours. If all pipes are left open simultaneously, it takes 66 hours to fill the empty tank. What is the relationship between M and N?
[XAT 2016]

M : N =1:1= 1 : 1
M : N =2:1= 2 : 1
M : N =2:3= 2 : 3
M : N =3:2= 3 : 2
None of the above

Question 3

A mother along with her two sons is entrusted with the task of cooking Biryani for a family get together. It takes 3030 minutes for all three of them cooking together to complete 5050 percent of the task. The cooking can also be completed if the two sons start cooking together and the elder son leaves after 11 hour and the younger son cooks for further 33 hours. If the mother needs 11 hour less than the elder son to complete the cooking, how much cooking does the mother complete in an hour?
[IIFT 2013]

33.33%33.33 \%
50%50 \%
66.67%66.67 \%
None of the above

Want to read the full content

Unlock this content & enjoy all the features of the platform

Subscribe Now arrow-right
videovideo-lock