CAT 2025 Lesson : Time & Work - Negative Work, Alternating Work & Past Questions
5. Negative rate of completion
Negative rate of completion questions are typically pipes, drains/leaks and tanks based. For instance, Pipe A and Pipe B can fill a tank in 2 hours and 4 hours while drain C can empty a tank in 6 hours. If all three are open at the same time, how long does it take to fill an empty tank?
In such questions the efficiency of a leak, or something undoing the work, will be negative.
Example 19
Tap X can fill a tank in 4 hours and tap Y can fill the same tank in 6 hours. A drain in the bottom of the tank can empty a full tank in 12 hours. If the two taps and the drain are opened at the same time, how long does it take an empty tank to be filled?
Solution
Portion of tank filled by taps X and Y in 1 hour are 41 and 61 respectively.
Portion of tank emptied by the drain in 1 hour is 121.
Portion of tank filled in 1 hour =41+61−121=31
Time taken to fill the tank =3 hours
Alternatively
Let the tank's capacity be LCM(4,6,12)=12 units.
Taps X and Y fill the tank at the rate of 412= 3 units/hr and 612 = 2 units/hr respectively.
The drain empties the tank at the rate of 1212 = 1 unit/hr
When all are open, rate of filling =3+2−1 = 4units/hr
Time taken to fill the tank =412=3 hours
Answer: 3 hours
Example 20
Pipes A and B take 5 hours and 8 hours respectively to fill an empty tank. Both the pipes are turned on at the same time. Exactly after two hours, a leak develops due to the pressure in the tank. It, therefore, takes 2 more hours for the tank to be filled. If the water flowing out of the leak was at a steady rate, how long would it take a filled tank to be emptied by the leak?
Solution
Let the leak take x hours to empty the tank.
Portion of the tank filled by the 2 pipes in 2 hours is 2(51+81)=2013
As it takes 2 more hours to fill the remainder of the tank, which is 1−4026=207.
2(51+81−x1)=207
⇒4013−407=x1
⇒ x=320 = 6hrs40mins
Alternatively
Let the tank's capacity be LCM(5,8)=40 units.
Pipes A and B fill the tank at the rate of 540 = 8units/hr and 840 = 5units/hr respectively.
Volume filled by A and B in 2 hours =2×(8+5)=26 units
Let the leak empty the tank at the rate of xunits/hr.
Volume of tank that is empty =40−26 = 14units
Volume filled by A, B and the leak in the next 2 hours =2×(8+5−x)=14
⇒ 26−2x=14
⇒ x = 6units/hr
Time taken by the leak to empty the tank =640=320 = 6hrs40mins
Answer: 6 hrs 40 mins
Example 21
A pipe usually takes 3 hours to fill an empty tank with water. However, on a particular day, it took 7.5 hours to fill the tank due to a leak it had developed. Then, how many hours would the leak take to empty a full tank?
Solution
Let the time taken by the leak to empty a full tank be t.
31−t1=7.51 ⇒ t1=31−152
⇒t=15
Answer: 5
6. People or objects working alternately
These questions involve objects or group of objects with different efficiencies taking turns and working. In these questions you need to calculate the portion of work completed in a cycle and then find out the point where a single person or object's work would render the work complete. The Parts Method is best to use here.
Example 22
When working alone, A, B and C take 12,15 and 24 days to complete a project. A works alone on the project on the first day, B works alone on the second day and C works alone on the third day. This pattern continues with each of the individuals working alone every 3 days. In how many days is the work completed?
Solution
Portion of work completed every 3 days =121+151+241=12010+8+5=12023
Let's look at the work as involving 120 parts. A, B and C can finish 10,8 and 5 parts in a day respectively and in 3 days 23 parts of work get completed.
In 5 such cycles involving 15 days, 5×23=115 parts get completed and 5 are remaining.
It's A's turn now, who can complete 10 parts in a day. Since there are 5 parts left, A can complete in 105=0.5 day. Therefore, the work gets completed in 15.5 days.
Answer: 15.5
Example 23
A and C are pipes that take 10 minutes and 60 minutes to fill a tank. B and D are leaks that take 40 and 24 minutes to empty a tank. At any given time only a tap or a drain is open. A is turned on for the first minute, B is then turned on for the second minute, C for the third, D for the fourth, A for fifth, B for the sixth and so on. This is repeated till the tank is full. How long does it take for the tank to be filled?
Solution
In one cycle of 4 minutes, portion of tank filled =101−401+601−241=12012−3+2−5=1206
Once again, the denominator can be looked at as the total work (i.e., 120 parts). In one cycle of 4 minutes, 6 parts are filled. Parts of tank filled by Pipe A, Leak B, Pipe C and Leak D are +12,−3,+2 and −5 respectively.
The maximum that a pipe can fill in 1 minute is Pipe A which is 12 parts. So, we can find out the number of cycles that fill 120−12=108 parts to provide for the possibility of a pipe filling the rest of the tank.
Therefore, in 18 cycles or 72 minutes, 18×6=108 parts are filled and 12 parts are remaining. As it is A's turn for the 73rd minute and it fills 12 parts, the work is complete in 73 minutes.
Answer: 73 minutes
7. Past Questions
Question 1
There's a lot of work in preparing a birthday dinner. Even after the turkey is in oven, there are still the potatoes and gravy, yams, salad, and cranberries, not to mention setting the table. Three friends, Asit, Arnold, and Afzal, work together to get all of these chores done. The time it takes them to do the work together is six hours less than Asit would have taken working alone, one hour less than Arnold would have taken, and half the time Afzal would have taken working alone. How long did it take them to do these chores working together? [CAT 2001]
20 minutes
30 minutes
40 minutes
50 minutes
Observation/Strategy 1) We can represent the individual time taken in terms of the total time taken and form an equation.
Let the time taken by all 3 together to complete the work be t.
Time taken by Asit, Arnold and Afzal are t+6,t+1 and 2t respectively.
When all 3 work together, t+61+t+11+2t1=t1
⇒ t+61+t+11=t1−2t1
t+1+6(t+6)(t+1)=2t1
⇒ 4t2+14t=t2+7t+6
⇒ 3t2+7t−6=0
⇒ 3t2+9t−2t−6=0
⇒ (3t−2)(t+3)=0
t=32,−3 [Negative value is rejected]
Therefore, time taken together is 32 hours or 40 minutes.
Answer: (3) 40 minutes
Question 2
A water tank has M inlet pipes and N outlet pipes. An inlet pipe can fill the tank in 8 hours while an outlet pipe can empty the full tank in 12 hours. If all pipes are left open simultaneously, it takes 6 hours to fill the empty tank. What is the relationship between M and N? [XAT 2016]
M : N =1:1
M : N =2:1
M : N =2:3
M : N =3:2
None of the above
Observation/Strategy 1) From the given data, we will be able to form just 1 equation on portion of work completed in an hour. We shall try finding the ratio with this.
Portion of tank filled in an hour when M inlet and N outlet pipes are opened is 8M−12N=61
⇒ 243M−2N=61
3M−2N=4
As there is a constant in this equation, we will not be able to find M : N.
Answer: (5) None of the above
Note that (M, N) can take values like (2,1), (4,4), etc. The ratios for these are 2:1,1:1, etc. So, there is no unique ratio.
Question 3
A mother along with her two sons is entrusted with the task of cooking Biryani for a family get together. It takes 30 minutes for all three of them cooking together to complete 50 percent of the task. The cooking can also be completed if the two sons start cooking together and the elder son leaves after 1 hour and the younger son cooks for further 3 hours. If the mother needs 1 hour less than the elder son to complete the cooking, how much cooking does the mother complete in an hour? [IIFT 2013]
33.33%
50%
66.67%
None of the above
Observation/Strategy
1) As 3 of them complete 50% of the work in 30 mins, they complete the full work in 1 hour.
2) Work gets completed if elder son works for 1 hour and younger son works for 4 hours.
3) Mother takes 1 hour less than elder son to complete the work.
Let the time taken by elder son and younger son to individually complete the work be x and y hours respectively. Therefore, the mother takes x−1 hours to complete the work.
When the elder and younger sons work for 1 and 4 hours respectively, x1+y4=1y1=41−4x1
When all three of them work together, x−11+x1+y1=1x−11+x1+41−4x1=1
x−11+4x3=43(4(x2−x4x+3x−3)=43
⇒ 7x−3=3x2−3x3x2−10x+3=0
(3x−1)(x−3)=0
x =31,3 [31 is not possible as this would result in time taken by mother to be negative]
Time taken by mother working alone =3−1=2 hours
Portion of work completed by mother in 1 hour =21=50%
Answer: (2) 50%
Want to read the full content
Unlock this content & enjoy all the features of the platform