+91 9600 121 800

Plans

Dashboard

Daily & Speed

Quant

Verbal

DILR

Compete

Free Stuff

calendarBack
Quant

/

Arithmetic II

/

Time & Work

Time And Work

MODULES

Basics & Worker-Day Method
Worker-Day Method
Unitary Method
Relative Efficiencies
Negative Work, Alternating Work & Past Questions

CONCEPTS & CHEATSHEET

Concept Revision Video

SPEED CONCEPTS

Time & Work 1
-/10
Time & Work 2
-/10
Time & Work 3
-/10

PRACTICE

Time & Work : Level 1
Time & Work : Level 2
Time & Work : Level 3
ALL MODULES

CAT 2025 Lesson : Time & Work - Worker-Day Method

bookmarked

2.1 Completion of work on schedule

2.1.1 Some workers had to leave

In the following two examples, two methods have been outlined. Product constancy is the recommended and the quickest method, if you are sound in the logic to be applied. Otherwise, we suggest you use the standard worker-day approach.

Example 3

121212 men can build a wall in 202020 days. 555 days after they started working, 333 of them had to leave. If no other worker leaves or joins this group, what is the expected delay (in days) in construction?

Solution

121212 men worked for 555 days and then 333 men left. Let's define overall work as 12×20=24012 \times 20 = 24012×20=240 man-days.

Work completed in
555 days =12×5=60= 12 \times 5 = 60=12×5=60 man-days

Work Remaining
=240−60=180= 240 - 60 = 180=240−60=180 man-days

As remaining work is completed by
999 workers in xxx days,
9×x=1809 \times x = 1809×x=180
⇒
x=20 x = 20x=20

Total time taken
=20+5=25= 20 + 5 = 25=20+5=25 days

This is
5\bm{5}5 days more than the initial time taken of 202020 days.

Alternatively (Product Constancy)

After
121212 men worked for 555 days, 151515 days of work is left. However, 333 of the 121212 men left.

As number of workers decreased by
14\dfrac{1}{4}41​, the time taken would have increased by 14−1\dfrac{1}{4 - 1}4−11​.

Work Delay
=13×15== \dfrac{1}{3} \times 15 ==31​×15= 5\bm{5}5 days

Answer:
555 days


Example 4

888 women take 151515 hours to complete a piece of work. 999 hours after the 888 women started working, some of them had to leave. If it took a total of 171717 hours to complete the work, how many women left at the end of 999 hours?

Solution

Total work =8×15=120= 8 \times 15 = 120=8×15=120 women-hours (w−h)(w-h)(w−h)

Work completed in
999 hours =8×9=72w= 8 \times 9 = 72w=8×9=72w − h- \ h− h

Remaining work
(120−72=48w−h)(120 - 72 = 48 w-h)(120−72=48w−h) is completed in 888 more hours.

Number of women left
=488=6= \dfrac{48}{8} = 6=848​=6 women

Number of women who left
=8−6== 8 - 6 ==8−6= 2\bm{2}2 women

Alternatively (Product Constancy)

After
888 women worked for 999 hours, instead of taking 666 more hours, it took 888 more hours to finish the work.

As time increased by
13\dfrac{1}{3}31​, women would have decreased by 13+1=14\dfrac{1}{3+1} = \dfrac{1}{4}3+11​=41​.

Number of women who left
=14×8== \dfrac{1}{4} \times 8 ==41​×8= 2\bold22 women

Alternatively

888 women work for the first 999 hours in both scenarios. So, this can be ignored.

888 women work for the remaining 666 hours in a normal scenario. When a few women left, the remaining xxx women took 888 hours to complete the work.

As the work done is the same in both the scenarios,
8×6=x×88 \times 6 = x \times 88×6=x×8
⇒
x=6 x = 6x=6

∴\therefore∴ Number of women who left =8−6== 8 - 6 ==8−6= 2\bm{2}2 women

Answer:
222 women


2.1.2 Wrong assessment of time taken to complete

As stated in
2.1.12.1.12.1.1, apply the product constancy method, only if you're sound in this logic.

Example 5

Kunal takes a contract to construct a warehouse in 606060 days and deploys 404040 of his men for this job. At the end of 202020 days, if only 25%25 \%25% of the construction is complete, how many more men does he need to deploy on this project, in order to complete the construction on schedule?

Solution

Work done by 404040 men in 202020 days =20×40=800= 20 \times 40 = 800=20×40=800 man-days

If this is
25%25 \%25% of the total work, then total work =800×4=3200= 800 \times 4 = 3200=800×4=3200 man-days

Work remaining after
202020 days =3200−800=2400= 3200 - 800 = 2400=3200−800=2400 man-days

Time left to complete the work on schedule
=60−20=40= 60 - 20 = 40=60−20=40 days

Number of men required to complete the work on schedule
=240040=60= \dfrac{2400}{40}= 60=402400​=60 men

Extra men required
=60−40=20= 60 - 40 = 20=60−40=20 men

Alternatively (Product Constancy)

25%25 \%25% of the work is completed by 404040 men in 202020 days. So, with 404040 men, the remaining 75%75 \%75% of the work will be completed in 606060 more days.

However, the remaining work is to be completed in
404040 more days.

So, if time taken decreases by
13\dfrac{1}{3}31​, then men required will increase by 13−1=12\dfrac{1}{3 - 1} = \dfrac{1}{2}3−11​=21​

Extra men required
=12×40=20= \dfrac{1}{2} \times 40 = 20=21​×40=20 men

Answer:
202020 men


2.1.3 Several variables influencing work

In these questions, work can be expressed as area, volume, etc. The same can be expressed as worker-hours or worker-days as well. These two works will be directly proportional to each other. We can then use variation to solve these questions.

Example 6

808080 workers can tile a rectangular floor of dimensions 80m×72m80\text{m} \times 72\text{m}80m×72m in 404040 hours. How many hours will it take 505050 workers to tile a floor of dimensions 90m×60m90 \text{m} \times 60 \text{m}90m×60m?

Solution

It takes 80×4080 \times 4080×40 worker-hours to tile an area of 80×7280 \times 7280×72 m2\text{m}^{2}m2.

Let
ttt hours be the time taken by 505050 workers. It takes 50×t50 \times t50×t worker-hours to tile an area of 90×6090 \times 6090×60 m2\text{m}^{2}m2.

Here, there is a direct relationship between area, which is the work to be completed, and worker-hours.

80×4050×t=80×7290×60\dfrac{80 \times 40}{50 \times t} = \dfrac{80 \times 72}{90 \times 60}50×t80×40​=90×6080×72​



⇒
85×40t=89×65\dfrac{8}{5} \times \dfrac{40}{t} = \dfrac{8}{9} \times \dfrac{6}{5}58​×t40​=98​×56​

⇒
t=t =t= 60\bm{60}60 hours

Answer:
606060 hours


For additional variables in a
333-dimensional figure and hours per day worked, the approach remains the same.

Example 7

505050 workers take 888 days to build 666 walls that are each 40m40 \text{m}40m, 50m50 \text{m}50m and 60m60 \text{m}60m in length, breadth and height respectively, working 666 hours on each day. If 606060 workers work 999 hours a day for 666 days, then how many wall of dimensions 54m×30m×40m54 \text{m} \times 30 \text{m} \times 40 \text{m}54m×30m×40m can they build?

Solution

This question has more variables than those in example 666. However, the approach remains the same. Let nnn be the number of walls built in the second case.



50×8×660×6×9=6×40×50×60n×54×30×40\dfrac{50 \times 8 \times 6}{60 \times 6 \times 9} = \dfrac{6 \times 40 \times 50 \times 60}{n \times 54 \times 30 \times 40}60×6×950×8×6​=n×54×30×406×40×50×60​

⇒
n=15n = 15n=15 walls

Answer:
151515 walls

Want to read the full content

Unlock this content & enjoy all the features of the platform

Subscribe Now arrow-right
videovideo-lock